CON 290 Exam 1 ALL ANSWERS 100% CORRECT FALL-2021
SOLUTION GUARANTEED GRADED A+
Content
User
Course CON290_20017-;01/27/2021-CON 290 Contract Administration and
Negotiation Techniques in a Supply Environment
Test Exam 1
Started
Submitted
Status Completed
Attempt
Score
Time
Elapsed
Results
Displayed
54 out of 60 points
1 hour, 55 minutes
Submitted Answers, Correct Answers, Incorrectly Answered Questions
• Question 1
8-2
0 out of 2 points
Joseph is the contracting officer on an R&D Cost Plus Fixed Fee (CPFF) “completion
form” contract with an estimated cost of $100,000. The negotiated fee is $12,000,
or 12% of estimated cost. The contractor has advised Joseph that they anticipate it
will actually cost $110,000 to complete the work and the Government has increased
funding accordingly. What final price will Joseph pay upon successful completion of
this effort, assuming final allowable cost comes in at $110,000?
Selected
Answer: $123,2
00
Correct
Answer: $122,0
00
• Question 2
8-2
Under a CPFF contract, the final amount that will be paid is:
Selected
Answer: Allowable incurred cost plus a
fixed fee
2 out of 2 points
Correct
Answer: Allowable incurred cost plus a
fixed fee
• Question 3
0 out of 2 points
1 / 2
4-3
As part of an internal contract review, Edward finds a contract that was solicited
under “other than full and open competition”. He locates the Justification &
Approval file and finds the Contracting Officer identified FAR 6.302-1 and FAR 6.302-
2 listed as the justification. Which of the following statements is true regarding this
justification?
Selected
Answer: This is compliant with FAR subpart 6.3.
Correct
Answer: The use of these two exceptions is a violation of FAR subpart 6.3.
• Question 4
2 out of 2 points
7-4
Given an acquisition setting where there are highly uncertain and speculative labor
hours, an uncertain labor mix, and/or speculative material requirements necessary
to perform the contract, which contract type would be most appropriate?
Selected
Answer: Cost plus fixed
fee
Correct
Answer: Cost plus fixed
fee
• Question 5
8-5
2 out of 2 points
You are in the process of negotiating a CPFF completion type contract for a new gun
turret. You intend to provide Government-furnished property (GFP) for some of the
required equipment. The contractor objects, stating that reliance on GFP could affect
its ability to deliver a working turret within the contract schedule. How should you
respond?
Selected
Answer: Point out that FAR 52.245-1, “Government Property” allows the
contractor to request equitable adjustment for cost or schedule impacts
caused by Government provision of GFP.
Correct
Answer: Point out that FAR 52.245-1, “Government Property” allows the
contractor to request equitable adjustment for cost or schedule impacts
caused by Government provision of GFP.
• Question 6
2 out of 2 points
10-8
You are evaluating a proposal that requires an analysis of Facilities Capital Cost of
Money (FCCOM). Using the following information, as appropriate, calculate the
Facilities Capital Employed amount. (Use DD Form 1861 for FCCOM.)
Company-wide allocation base for Engineering Overhead pool: $12,700,000
Powered by qwivy (www.qwivy.org)
2 / 2
Version | 2021 |
Category | Exam (elaborations) |
Pages | 10 |
Language | English |
Comments | 0 |
Sales | 0 |
{{ userMessage }}