TI F.P 100,23 Agile Exam Questions and Answers

TI F.P 100,23 Agile Exam Questions and Answers

1- What does NOT match with Agile Manifesto?

 Process and tools over individuals and interactions

 Working software over comprehensive documentation

 Responding to change over following a plan

 Contract negotiation over customer collaboration

2- Which of the following statements about changing requirements in software

development, are correct?

 In traditional way of software development, once the requirements are base lined,

further changes should undergo heavy change control process

 Changes are acceptable till design but once development starts, any further changes

should be rejected

 In traditional way of software development, once the requirements are base lined,

further changes can be easily accepted with light process

 Organizations must adapt to rapidly changing market conditions to stay relevant in

business

3- Which of the following statements BEST describe why Agile is winning?

 Products produced by an Agile approach are cheaper than those produced by any

other approach

 Agile increases the chances of delivering early business value to the market and quickly

incorporate the feedback from the market usage

 Products have faster time to market but may not meet immediate customer needs

 Products are expensive when compared with products produced by other approaches,

but are of top quality.

4- Why were the `practitioners of alternative software development methods` not

satisfied with the traditional waterfall method?

 Waterfall is not a lightweight process

 The practitioners did not like to work in a formal system and hence did not like any

‘methodology’ at all

 Waterfall experience did not add value to their resume

 Waterfall model failed to meet the demand for speed and was not friendly towards

changing business needs and priorities

5- Which of the following BEST represent the Scrum approach to planning?

 Planning is a continuous activity done faintly by Scrum Master and Product Owner

 Detailed planning is done upfront and not revisited

 Whole team together does just enough upfront planning followed by continuous

planning throughout the project

 Only planning in Scrum is one of the planning events

6- How should work be allocated to the team in a Scrum project?

 The Scrum Master must assign tasks to individuals

 Team members must volunteer for tasks appropriate to their skills

 The complex tasks must be allocated by the Scrum Master

 Tasks must be allocated to team members by the Product Owner

 While senior team members volunteer for tasks, juniors must be assigned takas by the

Scrum Master

No comments found.
Login to post a comment
This item has not received any review yet.
Login to review this item
No Questions / Answers added yet.
Version latest
Category Exam (elaborations)
Pages 14
Language English
Comments 0
Sales 0
Recently viewed items

We use cookies to understand how you use our website and to improve your experience. This includes personalizing content and advertising. To learn more, please click Here. By continuing to use our website, you accept our use of cookies, Privacy policy and terms & conditions.

Processing