TI F.P 100,23 Agile Exam Questions and Answers
1- What does NOT match with Agile Manifesto?
Process and tools over individuals and interactions
Working software over comprehensive documentation
Responding to change over following a plan
Contract negotiation over customer collaboration
2- Which of the following statements about changing requirements in software
development, are correct?
In traditional way of software development, once the requirements are base lined,
further changes should undergo heavy change control process
Changes are acceptable till design but once development starts, any further changes
should be rejected
In traditional way of software development, once the requirements are base lined,
further changes can be easily accepted with light process
Organizations must adapt to rapidly changing market conditions to stay relevant in
business
3- Which of the following statements BEST describe why Agile is winning?
Products produced by an Agile approach are cheaper than those produced by any
other approach
Agile increases the chances of delivering early business value to the market and quickly
incorporate the feedback from the market usage
Products have faster time to market but may not meet immediate customer needs
Products are expensive when compared with products produced by other approaches,
but are of top quality.
4- Why were the `practitioners of alternative software development methods` not
satisfied with the traditional waterfall method?
Waterfall is not a lightweight process
The practitioners did not like to work in a formal system and hence did not like any
‘methodology’ at all
Waterfall experience did not add value to their resume
Waterfall model failed to meet the demand for speed and was not friendly towards
changing business needs and priorities
5- Which of the following BEST represent the Scrum approach to planning?
Planning is a continuous activity done faintly by Scrum Master and Product Owner
Detailed planning is done upfront and not revisited
Whole team together does just enough upfront planning followed by continuous
planning throughout the project
Only planning in Scrum is one of the planning events
6- How should work be allocated to the team in a Scrum project?
The Scrum Master must assign tasks to individuals
Team members must volunteer for tasks appropriate to their skills
The complex tasks must be allocated by the Scrum Master
Tasks must be allocated to team members by the Product Owner
While senior team members volunteer for tasks, juniors must be assigned takas by the
Scrum Master